Activities in 2012

• Kubyin weir and two reservoirs, upper dam and lower dam with the total storage capacity of 6 million gallons and 45 million gallons respectively, were completed.
• The construction of electrical overhead line from Ye Paung Sone Power Station to the factory area was completed in 2012.
• The company had a great progress in the machinery shipment in 2012.
• The major construction and installation of machinery such as preheater and kiln was completed.
• 90% of overall foundation and civil work and 20% of installation works were finished by year end 2012.

WordPress Image Gallery Plugin